TIMELINE
TIMELINE
Initial Screening request - Non EIA - Solar & Battery Farm
March 2021
Amended Screening request
March 2022
Screening response - The Consents Unit - Non EIA Development
July 2022
3rd Community Consultation - Solar Development only
November 2022
Target Submission to The Consents Unit
November 2022
Resubmission of Screening request
January 2023
Amended Layout and land areas
The Energy Consents Unit
Application Submission
October 2023
Further Pre Application Consultation with Community
February 2023
23rd February 2023 Murroes Community Hall, 4.30pm - 7.30pm